Explore the application of KER13 to construction logistics by preparing a pilot to monitor loading/unloading activities at construction sites, improve understanding of construction logistics flows and assess how digital monitoring could support more efficient parking and delivery operations.
Mechelen focused their pilot activities on construction logistics, responsible for +/- 35% of urban logistics in the city. The city has limited data and information available on how much traffic a construction site generates. The pilot aimed to gather data on aspects such as delivery times and vehicle types and explore the potential use of a booking system to streamline deliveries. Although the camera was ultimately not installed due to implementation delays, several preparatory steps were completed, including identifying potential construction sites, coordinating with relevant city departments and discussing installation conditions with the contractor.
The monitoring solution needs to fit the characteristics of the testing site and logistics flow. Camera-based monitoring may not be suitable in every location. Practical conditions such as location, timing and power supply also need to be confirmed with the construction partner before installation.
Assess the local site, logistics flow and available monitoring infrastructure. Where cameras are unsuitable, consider alternative technologies such as sensors.
Local partners are important for implementation and testing. Their involvement can require significant time and effort, particularly where relationships do not already exist.
Identify relevant local stakeholders early. Link participation to activities or benefits that are relevant to them.
Data collection should remain simple and be planned alongside the pilot implementation. Data protection is particularly important when cameras or location data are involved. Surveys and stakeholder workshops can complement technical monitoring and generate useful implementation insights when physical testing is delayed or not feasible.
Cities should consider a plan to be compliant with local GDPR restrictions and select a method of monitoring the L/U space that is compliant with local regulations.
GDPR, privacy requirements and local rules and the construction-site timeline can strongly influence how the solution is implemented. Early involvement of relevant city functions is important.
Check local regulatory and administrative requirements early, involve the Data Protection Officer where appropriate, and allow sufficient time for approvals and internal coordination.
Implementation requires technical expertise and knowledge from different city departments and external partners. Knowledge gaps may emerge during implementation.
Identify required expertise and resources before implementation. Involve relevant city departments and external technical partners to address knowledge or capacity gaps.
Main takeaways from implementation





Action-oriented advice for future adopters